            TOTAL NUMBER OF MANPOWER                 TOTAL REMARKS
ITEM DESCRIPTION November, 2003 7 Days  
    28 29 30 1 2 3 4    
1 Project Manager 1 1 1 1 1 1 1 7  
2 Project Engineer  2 2 2 2 2 2 2 14  
3 QA/QC Enigineer 1 1 1 1 1 1 1 7  
4 Site Engineer 7 7 7 7 7 7 7 49  
5 Foreman 7 7 7 7 7 7 7 49  
6 Surveyor 2 2 2 2 2 2 2 14  
7 Safety Offecer 1 1 1 1 1 1 1 7  
8 Draftsman 4 3 3 3 3 3 3 22  
9 Administration  4 4 4 4 4 4 4 28  
10 Store Keeper 4 5 5 5 5 5 5 34  
11 Headman 22 25 24 22 23 24 22 162  
12 Time Keeper 8 9 8 7 7 7 8 54  
13 Security 6 6 6 6 6 6 6 42  
14 Carpenter 95 108 110 105 96 104 103 721  
15 Concreter 91 91 99 81 81 109 94 646  
16 Labour 64 65 68 60 59 70 65 451  
17 Maintenance 5 5 5 5 5 5 5 35  
18 Painting 38 35 34 42 41 44 38 272  
19 Crane Driver 1 1 1 1 1 1 1 7  
20 Equipment Operator 0 0 0 0 0 0 0 0  
21 Driver 2 2 2 2 2 2 2 14  
22 Barbender 9 11 0 14 14 27 9 84  
23 Electrician 5 5 5 5 5 5 5 35  
24 Welder & fitter 19 19 15 17 17 18 19 124  
25 Surveyor Boy 7 7 7 7 7 6 6 47  
                     
                     
                     
                     
  Grand Total 405 422 417 407 397 461 416 2925 418